Measure DD Executive Team Update
April 12,
2007
Project Updates
The attached spreadsheet shows the status of each project as
of 4-12-07. Some highlights include:
- The 12th Street
Reconstruction Project bid opening in December 2006 resulted in only one
bid, which was $9.3 million (26%) above the engineer’s estimate. The bid was rejected and we plan to
re-bid the project towards the end of this year. Fortunately, a large source of Federal
funding has become available and an application was submitted in March
2007. NEPA environmental work is
being prepared in support of the Federal funding application, and we are
doing additional CEQA work concurrently.
- The
Lake Merritt Pergola Renovation Project was completed, and a re-dedication
ceremony was held on March 3.
- Construction
continues on the Studio One Renovation Project, and it is 50% complete.
- The
structural work on the Municipal Boathouse continues. Unforeseen conditions encountered during
the foundation work include the discovery of contaminated soil under the former
pumphouse and deteriorating underground/underwater beams that need
extensive repair.
- The
Lakeside Park Fire Protection Project is complete.
- Bids
on the E.18th Street Historic Pier project will be opened on
April 16.
- In
March 2007 a contract was awarded for construction of a segment of the
Waterfront Trail at Alameda
Avenue, near the Fruitvale Bridge.
- .Also
in March, a contract was awarded for construction of a central irrigation
control system in Lakeside
Park.
A lawsuit filed against the City regarding the removal of
trees around Lake
Merritt has delayed
progress on landscaping projects around the Lake. Settlement discussions between attorneys are
ongoing.
One large impact to recreational use of the parks around Lake Merritt
is the presence of large numbers of Canada Geese, and their associated
waste. We have hired a consultant to
study the problem to identify options for goose management, including design
modifications that we can incorporate into our Measure DD projects. A community meeting on this issue, sponsored
by Councilmembers Nadel and Kernighan, will be scheduled for mid-June.
Project Expenditures
The attached spreadsheet shows project expenditures as of March 30, 2007. Approximately $28 million had been spent as
of that date, which is far less than was anticipated when the bonds were sold
in August 2003. Various unexpected
delays have prevented many projects from moving into the construction
phase. At Lake Merritt,
opposition to tree removals and parking lots resulted in a nine-month-long
public process to resolve the issues. A
lawsuit regarding tree removal is now causing additional delays. At the Estuary, the Union Point Park Project
is complete, but the adjacent Cryer Site Project is delayed as a remediation
plan for the unexpected soil contamination is negotiated with the State Water
Board. Several other Estuary projects have
been delayed due to the unwillingness of property owners, both public and
private, to grant the City easements for the Waterfront Trail.
To spend large amounts of money in a short period of time,
it is necessary to move projects into the construction phase, and we are
working on several fronts to accomplish this goal.
Fundraising
We have applied for a $2.5 million Federal appropriation for
the Lake Merritt projects.
We have applied for a grant for the Waterfront Trail through
the Regional Bike/Pedestrian Program, and it appears likely that we will
receive over $500,000.
We have applied for a grant for the Waterfront Trail through
the 2006 State Recreational Trails Program.
We have applied for a large grant for the 12th Street Project from the
Federal Highway Bridge Program, which we hope will result in a grant of several
million dollars.
State Proposition 84, the Clean Water Bond passed in November
2006, will provide funding opportunities for water-related projects. Details are being worked out through the State
legislative process, and when the program rules are published the City should
be well-positioned to compete for a share of these funds.
Questions or comments?
Contact Joel Peter, jmpeter@oaklandnet.com,
(510) 238-7276.