| Project
Name |
Project Budget
(excl. inflation) |
Series 2003A
Appropriation |
Project
Description |
Project Status |
| LAKE MERRITT |
|
$85,000,000 |
|
|
| 12th Street |
$47,250,000
|
$9,500,000 |
12th Street will be redesigned
into a tree-lined boulevard with signalized intersections and crosswalks and
a landscaped median. The redesign
would create significant new parkland at the south end of Lake Merritt Park,
remove unsafe and unsightly pedestrian tunnels, provide safer and continuous
access for pedestrians and bicyclists along the perimeter of Lake Merritt,
and improved access between the Kaiser Convention Center and Laney College.
Removal of the Lake Merritt Channel culvert at 12th Street will provide an
open-water bridged connection, and improve water flow, between the Lake and
the Estuary. Environmental benefits
include improved water quality and wildlife habitat. |
The
concept design for the 12th Street area has been completed and a community
meeting held in October, 2004 attended by over 150 participants. The master plan concept for 12th Street
has evolved from a linear alignment to a curved alignment. The curvilinear configuration will result
in better American Disabilities Act (ADA) accommodations, improves site
distances for automobiles, pedestrians
and bicycles while providing a traffic calming effect, intersects the channel
at a better angle (therefore minimizing the bridge length); and, the design
creates a potentially larger redevelopment area adjacent to the OUSD
administration building on 2nd Ave.
The scope of the traffic study was expanded to include a larger
geographic area and projections to year 2025. Parking study completed for Lakeshore and 1st Ave. area. Geotechnical drilling completed. Water-related permitting work underway.
Phase II soil testing completed.
Detailed design work is continuing.
Construction is scheduled to run from spring 2006 to Summer 2008. |
| Lake
Merritt Water Quality (Storm drain
filters, trash barriers, aeration, etc.) |
$5,600,000 |
$1,000,000 |
Improve
Lake Merritt’s water quality by installing trash barriers and aeration
fountains, implementing a goose management plan, retrofitting storm drain
inlets, and implementing other actions to reduce water pollution. |
In
July 2004, City Council adopted Resolution 78750 authorizing the
implementation of a variety of projects at Lake Merritt. Projects include installation of an
aeration fountain at Grand and Harrison; upgraded electrical service for the
existing aeration fountain located at the Pergola; an air diffuser system
pilot project and up to four storm water filter units in the Lake Merritt
watershed. Other projects that are
being considered include solar-powered circulation pumps, floating wetland
"restorer" units, and additional storm water filters. In January 2004 one storm water filter
unit was installed at Perkins and Bellevue in Lakeside Park. |
| Children's Fairyland |
$3,000,000 |
$3,000,000 |
Implementation
of facility master plan components including construction of a new pavilion
for puppet theatre presentations and special events; renovation of the puppet theatre; Grand
Avenue entry improvements; refurbishment of sets; repair of site drainage
system. |
Oakland
Children’s Fairyland, Inc. a local
nonprofit organization has contracted with the City to implement projects at
Children’s Fairyland. To date, the
non profit organization has completed survey work to address drainage issues
associated with animal waste, provide for undergrounding of utilities, and
provide for upgrades to existing circulation to accommodate emergency service
vehicle access. Ace Architects was
hired to provide architectural services.
Design development for a new theatre and multi-use complex and new
Puppet Theatre is complete and construction documents are projected to be
completed by April, 2005. Set
renovations to address dry rot will be initiated for the Thumbelina Tunnel,
the Old West Junction and the Chapel of Peace beginning in January 2005. Council authorized a new agreement which
will allow Oakland Children’s Fairyland to manage the design and construction
of all these projects. |
| Restore Municipal Boathouse (1520 Lakeside Drive) |
$8,235,000 |
$6,500,000 |
Restore
the Municipal Boathouse (1520 Lakeside Drive) to its original condition, with
a new program to accommodate public uses (such as boat storage, a restaurant
and a meeting hall) rather than City offices. Public access to the dock would be improved, the arches would
be reopened to allow for boat storage, landscape and irrigation would be
improved, and the parking lot would be redesigned to improve shoreline
circulation. |
The
Office of Parks and Recreation has relocated downtown. Environmental
consultant completed sampling and testing building materials for lead paint
and asbestos. Award of a contract for hazardous material abatement and soft
demolition work is scheduled for February 1, 2005, with construction
beginning in March. The City
contracted with the design firms of WRT and Murakami Nelson to complete
design work associated with this project.
Schematic design is complete and a community meeting was held on
August 12, 2004 to provide an overview of project components. Further design work is underway. Part of
this task involves working with the City’s Landmarks Advisory Board so that
the facility can be considered for both State and National landmark status in
the future. Sustainable design
components will make this project the City’s first LEED-certified (Leadership
in Energy and Environmental Design) “green” building. A second community
meeting will be held February 23, 2005.
Plans are scheduled for bidding in June 2005, with construction
beginning in the Fall. |
| Renovate
and restore Lakeside Park Sailboat House
|
$7,425,000 |
$1,250,000 |
The Lake
Merritt Sailboat House will be
renovated to reveal its historic character, and improvements would be made to
the parking lot and landscaping. The
building will accommodate recreational programs, boat storage, meeting rooms
and other public uses. |
The
Sailboat House Renovation project was originally scheduled to begin in 2006,
but consultant selection process was initiated in November 2004. The February
8, 2005 Measure DD staff report is recommending that this project be put on
hold until Series B to provide for additional funding to the Municpal
Boathouse and Lake Merritt Bicycle and Pedestrian Path projects . |
| Lake Merritt Systemwide Projects |
$16,375,000 |
$3,350,000 |
Lake Merritt
system-wide renovation of restrooms to be adequately clean, lighted,
ventilated and maintained; adaptive reuse of miscellaneous buildings; and
installation of street furnishings such as drinking fountains and trash and
recycling receptacles, directional signs, public art, interpretive signs,
historic markers and informational kiosks. |
Specific
project allocations are being determined based on enabling language, with
technical and community input. See
Exhibit E of the February 8, 2005 Measure DD Progress report for specific
project recommendations. |
| Repair Lake Merritt
Retaining Walls |
$3,715,000 |
$2,000,000 |
Repair or replace over 2 miles
of retaining walls surrounding
Lake Merritt. Currently, many of the
retaining walls are cracking, spalling, tilting, eroding, settling and, thus,
in generally poor condition, and funds are needed to reconstruct or
strengthen foundations, provide shoring to brace walls, install proper
drainage measures around the walls to prevent erosion, and/or to patch and
restore wall surfaces |
Projects
funded under this category include: Repairs to the Sailboat House retaining
walls and walls just west of the Sailboat House ($200,000 and $325,000); East
18th Pier ($550,000); Bird Sanctuary retaining wall repairs ($350,000);
Municipal Boathouse parking lot retaining wall repair ($250,000); and
retaining wall repairs within the vicinity of east 18th ($325,000). Where feasible, repair work will be
incorporated into the scope of work for other Measure DD projects directly
impacted by the proposed improvements. Retaining wall project timelines would
commensurate with established timelines for each of the related projects or
be developed independently to coincide with the master schedule for Series A
projects. E.18th dock design being
discussed with consultant and with Landmarks Board, and geotechnical drilling
has been completed. |
| Widen and improve pedestrian and bicycle paths and lanes around
Lake Merritt. |
$9,800,000 |
$3,000,000 |
Widen the
borders of Lake Merritt Park to
increase parkland by narrowing Lakeside Drive and Lakeshore Avenue. The street redesigns would allow the
creation of a wide multi-use path and bike lanes around Lake Merritt, and
would improve connections, both physical and visual, to perimeter parks such
as Pine Knoll Park, Snow Park and Athol Park. |
WRT's surveyors
completed mapping park and streets around Lake. Community meeting was held August 12. Schematic design is nearly complete and a second community
meeting will be held February 23, 2005.
Construction is scheduled to begin in Fall 2005. |
| El
Embarcadero reconfiguration |
$2,120,000 |
$2,000,000 |
Make Eastlake Park safer for
pedestrians, while expanding usable park space, by consolidating the two
separate El Embarcadero roadways into one. Part of the “Grand Lake Green Link”
project. |
This
project has been incorporated into the Scope of Work for the widening of the
Park Borders project and is being designed by WRT as well. WRT's surveyors
completed mapping park and streets around Lake. Community meeting was held August 12. Schematic design is nearly complete and a second community
meeting will be held February 23, 2005.
Construction is scheduled to begin in Fall 2005. |
| ESTUARY
WATERFRONT ACCESS, PARKS AND CLEAN-UP (BAYTRAIL) |
|
$53,000,000 |
|
Consultant Hood Design has begun
enhancing design standards, lighting and signage, and is providing design
guidance for waterfront projects.
Draft standards will be reviewed by Port, BCDC, and community in
January and February 2005. |
| Estuary
Park |
$14,483,972 |
$2,080,000 |
Two alternatives are being
explored for this site. Alternative A
address the site as it currently exits.
Alternative B assumes acquisition of the Cash and Carry Warehouse from
the Port of Oakland to enlarge the open space from the existing 5 acres to 14
acres. Both alternatives reshape the
shoreline, provide access along the water's edge and redesign parking to
provide for additional landscape areas and a green edge. |
Plans will be discussed for
Estuary Park in conjunction with the review process of the proposed Oak to
Ninth mixed use development project.
The sponsor is presently in the environmental review process; a series
of community meetings and interviews will be conducted as a part of the
process. The Measure DD project is currently on hold.
|
| 10th Avenue Marina |
$316,694 |
$200,000 |
Minor upgrades
to the paving and incorporation of standardized trail elements such as
signage and lighting. |
The City has contracted with
Wolfe Mason to begin design of this project.
This project has been grouped with the Brooklyn Basin/Marine Max
project, and the Brooklyn Basin to Embarcadero Cove project to create a larger
single project. Survey mapping is complete.
Work on this existing trail consists of installation of standardized
trail elements such as site furnishings and light markers. Design work will begin in February when
the trail elements are selected as part of the Development Standards being
developed by Hood Design. |
| Brooklyn Basin and Marine Max |
$3,727,366 |
$2,700,000 |
One
of the few vacant sites along the waterfront, Brooklyn Basin provides an
opportunity for a visual connection to the water from the freeway and
adjacent neighborhoods and opportunity for limited commercial development
combined with wetland restoration and shoreline access. |
This
project has been grouped with the 10th Avenue Marina project, and the
Brooklyn Basin to Embarcadero Cove project to create a larger single
project. Wolfe Mason Associates
completed survey, prepared base maps, and began preliminary design work. Phase II environmental testing is
complete. Lead contaminated soil is
present on the site and the cost to cure ranges from $350,000 to $500,000. Real Estate Division was negotiating
long-term lease from Port, but Port is now negotiating with a developer of a
marina and boat mall. If development
proceeds, BCDC will require the developer to construct the trail. The Measure DD project is on hold while
the developer negotiates with the Port. |
| Brooklyn Basin to Embracadero Cove |
$254,847 |
$235,000 |
Minimal
upgrades to the existing trail and incorporation of standardized signage and
lighting. |
The City has
contracted with Wolfe Mason to begin design of this project. This project has been grouped with the
Brooklyn Basin/Marine Max project, and the 10th Avenue Marina project to
create a larger single project. Survey mapping is complete. Work on this existing trail consists of
installation of standardized trail elements such as site furnishings and
light markers. Design work will begin
in February when the trail elements are selected as part of the Development
Standards being developed by Hood Design. |
| Livingston Pier |
$370,514 |
$340,000 |
The
pier is currently leased by the Port of Oakland to Vortex Diving through
2011. As a long term option, the
building could potentially be used for recreational/retail uses that relate
to the proposed skateboard park on the adjacent site. The trail would wrap
around the perimeter of the pier, and would incorporate standardized signage
and lighting. |
Public
Works will begin design of project improvements upon the completion of trail
development standards in February 2005. The project consists of a 150 foot
segment of trail to run across the front of the pier, serving as the primary
trail connection until such time as the entire pier becomes available. Until Vortex Diving relocates, pier will
remain off-limits to the public. |
| Cryer Site |
$1,650,326 |
$1,450,000 |
Adjacent
to Union Point Park, the existing building is seen as being converted for
community uses. Other improvements
would include restoration of a sandy beach along with some of the piers. The site will be landscaped and include
parking adjacent to the building. |
As-needed
architectural consultant KPA completed evaluation of existing building
conditions. Additional funding is
needed to perform a feasibility study and look at programming options for a
community facility integrated with a commercial componenet. Wolfe-Mason is working on a schematic
plan, with input from Walter Hood.
Hazardous materials on this site are extensive with a large amount of
metallic slag (a byproduct of steel manufacturing) needing to be
removed. Remediation is anticipated
to cost a minimum of $900,000. A
remediation plan is being prepared and it will be incorporated into the
schematic design phase. The
remediation plan is due to be completed in January 2005 and submitted to the
State Water Resources Board for review.
Schematic design work should be completed in February 2005, with a
community meeting to be held in early March.
|
| Union Point Park |
$4,000,000 |
$4,000,000 |
The
new 9 acre waterfront park will begin construction with $4 million in funding
from Measure DD. |
Phase
One construction (grading/paving) by Bay Cities completed. Phase Two (park
landscaping) by Valley Crest began Sept. 7. Project projected to be completed
by September 2005 |
| Park Street Bridge |
$1,611,200 |
$300,000 |
Two
alternatives are proposed for the trail connector at the Park Street
Bridge. The first option considers a
floating connection over the water.
The option would introduce ramps leading to a floating pier under the
bridge connecting back via a ramp to the other side. The second option is an at-grade standard
concrete trail connection at the bridge.
This option would require modification of existing traffic signals. |
Design
consultant Moffatt & Nichol is doing preliminary design and permitting
work, with a range of trail route and design options provided for review in
January 2005. Project is impacted by
Army Corps of Engineers, owner of the Tidal Canal permitting
requirements. Consultant is defining
Coast Guard issues regarding navigable channel and permit issuance, and
discussing design with bridge owner (Alameda County). |
| Park Street Triangle |
$2,198,368 |
$46,000 |
The
Park Street triangle currently includes 7-11 and Niko's Family Restaurant.
The site is a virtual gateway to the waterfront for travelers along 23rd
Avenue and Park Street Bridge and is a terminus for bicyclists along the
Embarcadero. The site is located
midpoint between the trail connecting Jack London Square and the MLK Regional
Shoreline and can serve as a starting point for a journey along the
waterfront. A comprehensive traffic
study of the area would be required to provide final alternatives for this
site. |
A comprehensive traffic study of
the area will be initiated as a funding propsal to to further understand the
various alternatives available to achieve project objectives. The City of Alameda and Alameda County are
project partners. |
| Pier 29 Restaurant |
$1,731,707 |
$1,200,000 |
The Pier 29
Restaurant is built right to the edge of the waterfront and does not provide
room to incorporate a trail connection on land. There are several options on this site. One option is to acquire the site and
incorporate the trail along the water's edge. Another alternative is to rebuild the restaurant closer to the
street allowing for trail access along the water's edge. A third is to run trail in water,
bypassing restaurant. |
Design is
dependent upon adjacent trail under bridge. Moffatt & Nichol has begun
preliminary design in coordination with bridge trail design. See Park St. bridge notes. |
| Derby Street Park |
$808,141 |
$268,000 |
There
are three streets between park Street Bridge and Fruitvale Bridge that
terminate at the waterfront - Peterson, Derby, and Lancaster Streets. These streets are ideal locations for
pocket parks, providing observation areas along the waterfront. Derby Street park is designed to
accommodate the need for truck loading and unloading, Cal Crew access to the
waterfront and open space. |
Real
Estate Division has completed a "street search" and determined that
City owns underlying fee. Phase II
soil testing is complete, and no serious contamination was found. This project has been grouped with the
Oakland Museum Women's Board site project, and the Alameda Avenue project to
create a larger single project.
Design consultant Amphion has begun design work. Community review of schematic plans will
be in February 2005. |
| Oakland Museum Womens Board Site |
$627,334 |
$580,000 |
The
trail would run behind the Women's Board warehouse and will include a
cantilevered walkway to provide a 12 foot wide trail that is adequately
separated from the museum building.
The trail would include standardized signage, lighting and furniture
elements. |
City
surveyors completed field work, and prepared legal description. Real Estate Division with assistance from
the City Attorney's Office has negotiated an easement agreement. The City is awaiting receipt of the
excuted agreement. Phase II soil
testing is complete, and no serious contamination was found. This project has been grouped with the
Derby Street project, and the Alameda Avenue project to create a larger
single project. Design consultant
Amphion has begun design work.
Community review of schematic plans will be in February 2005. |
| Lancaster Street to Fruitvale Bridge |
$156,234 |
$130,000 |
This
segment of trail includes shoreline protection, introduction of a concrete
trail, associated trail landscaping, standardized signage and lighting. |
Trail
design is dependent upon design of adjacent Fruitvale Bridge trail. Moffatt & Nichol is doing preliminary
design in conjunction with bridge trail design. Real Estate Division to
negotiate easement w/property owner Fairn & Swanson once trail alignment
established. See Park St. bridge
notes. |
| Fruitvale Bridge |
$1,522,532 |
$900,000 |
Two
alternatives are proposed for the trail connector at the Fruitvale
Bridge. The first option considers a
floating connection over the water.
This option would introduce ramps leading to a floating pier under the
bridge connecting back via a ramp to the other side. Alternative B assumes an at-grade
connection across the bridge. Ramps would be included to bridge the 4 foot
difference in grade between the trail elevation and the elevation at the
bridge. This alternative includes
alterations to existing traffic signals.
Alternative A is recommended in the Waterfront Trail Feasibility Study
as it avoids conflicts with the railroad bridge fencing and equipment. |
Design
consultant Moffatt & Nichol is doing preliminary design and permitting
work. See Park St. bridge notes. |
| Fruitvale to Alameda Ave |
$290,040 |
$200,000 |
This
segment of trail extends southeast of the Fruitvale Bridge along Alameda
Avenue. It will include the
installation of 800 feet of standard concrete trail along with landscaping
and standardized signage and lighting. |
This
project has been grouped with the Derby Street project, and the Oakland
Women's Museum Board site project to create a larger single project.Phase II
environmental testing is complete, and no serious soil contamination was
found. Design consultant Amphion has
completed surveying work and has begun design work. Community review of schematic design is scheudled for early
March 2005. |
| US Audio |
$1,862,040 |
$1,100,000 |
The U.S. Audio/Capture
Technologies building extends to the top of the bank. The trail will be pier-supported and
cantilevered. |
Amphion
has completed topographic and boundary survey. Real Estate Division will negotiate easement. |
| High Street Bridge |
$1,463,515 |
$300,000 |
Two
alternatives are proposed for the trail connector at the High Street
Bridge. The first option considers a
floating connection over the water.
The option would introduce ramps leading to a floating pier under the
bridge connecting back via a ramp to the other side. The second option is an at-grade standard
concrete trail connection at the bridge.
This option would require modification of existing traffic
signals. Standardized lighting and
signage would be incorporated into the project design. |
Design
consultant Moffatt & Nichol is doing preliminary design work. See Park St. bridge notes. |
| Gallagher & Burke and Hanson Aggregate |
$1,937,148 |
$350,000 |
The
segment of trail adjacent to the Gallagher & Burk asphalt plant is
proposed to be concrete pier supported walkway. Because the Hanson Aggregate facility uses water access for
delivery of materials, there is a cost associated with providing a secure
overhead conveyor system that would allow for materials to be transferred
from the barges to the site while allowing for shoreline trail access. The trail will incorporate associated
amenities such as standardized lighting and signage. |
Real
Estate Division will negotiate easement.
Because design is dependent upon adjacent High St. Bridge trail,
preliminary designs to be prepared together. Moffatt & Nichol is doing
preliminary design in coordination with bridge trail design. Draft of various
trail route and design options will be ready for review in January 2005. |
| 66th Avenue Gateway |
$5,829,132 |
$2,000,000 |
66th Avenue
would serve as a major gateway to the waterfront and provides a visible
connection between neighborhoods and the waterfront. A linear arrangement of trees along the
street frontage will reinforce the gateway connection and vertical markers
will further delineate the site.
Lighting would be minimal along the waterfront at this location in
order to reduce impacts to the marshlands and wildlife. |
Consultant
HQE completed topographic survey work. Design consultant The Planning
Collaborative is doing wetland study and preliminary design work. Interagency coordination with the Port of
Oakland and the East Bay Regional Park District is required due to underlying
ownership by the Port and lease agreements with the park district. Schematic
design is expected to be ready for community review in February 2005. |
| Environmental Remediation |
$1,200,000
|
$900,000 |
Allowance for
remediation as needed to cleanup sites listed for improvement in Series A of
Measure DD |
PWA
Environmental Services has evaluated existing hazmat documentation, and
completed additional soil testing at Brooklyn Basin, Cryer Site, Derby Ave,
Museum Board site, Lancaster St, Alameda Ave. and 66th Ave. Two sites, Brooklyn Basin and the Cryer
Site have significant soil contamination issues. The Brooklyn Basin project is on-hold, so no further work is
being done at this time. A
remediation plan for the Cryer Site is being prepared. The trail at the bridges and adjoining
properties will be tested once an exact trail alignment is determined. |
| LAKE
MERRITT TO ESTUARY CONNECTION (LAKE MERRITT CHANNEL) |
|
$27,000,000 |
|
|
| 7th
Street Flood Control Pump Station |
$16,000,000 |
$4,000,000 |
This
project is part of the plan to establish the connection, by foot and boat,
between Lake Merritt and the Estuary along the Lake Merritt Channel. Options being considered include
relocating the Alameda County Flood Control pump station and floodgates from
7th Street to 12th Street, relocating them to the Estuary, or leaving them in
place at 7th Street and building a by-pass channel. |
Bathymetry
survey of Lake bottom complete. URS
Corporation completed additional modeling of Lake Merritt water flows and
assessed cost and structural considerations to determine final location of
flood structure to maximize access and flood protection. It was found that complete relocation of
the station would provide minimal increase in water flows. Instead, Staff recommends installing a
by-pass channel for boats and large fish around pump station and improving
pedestrian/bike access. |
| YOUTH
AND PUBLIC RECREATION FACILITIES |
|
$20,000,000 |
|
|
| East
Oakland Aquatic, Sports and Recreation Facility |
$56,100,000 |
$1,000,000 |
Build the Oakland Family and
Aquatics Complex, a
150,000-square-foot indoor sports and recreation complex at the Ira Jinkins
Park, in East Oakland, complete with furnishings and equipment. Amenities would include swimming pools and
diving boards, basketball courts, running track, fitness center, teen
facilities, daycare center, and multi-purpose meeting rooms. |
Staff has
worked with ELS Architecture to provide alternative project scope(s) and
cost(s). $3 million State grant
awarded in October 2004. District 7
office is working with the City Administrator's Office to identify additional
funds. |
| Studio
One |
$10,000,000 |
$10,000,000 |
Renovate and
upgrade the 22,000-square-foot Studio One arts and culture center to address mandatory building codes, all
life-safety issues and deferred maintenance; provide temporary program during
construction; improvements to create opportunities for expanded programs and
classes (painting, drawing, sculpture, ceramics, photography and other arts);
provide some new furniture and equipment; and make the building accessible to
the disabled. |
Shah-Kawasaki
Architects has performed programming and concept design work and community
meetings were held on June 14 and October 25. Landmarks Board approved the schematic design. Detailed design work is continuing. Selection of a Public Art component will
occur in March 2005. Hazardous
materials abatement is scheduled to begin at the end of March 2005. Construction scheduled from Summer 2005
through Summer 2006. |
| CREEKS
AND WATERWAYS RESTORATION |
|
$10,000,000 |
|
|
| Creek
Restoration Projects |
$5,500,000 |
$1,700,000 |
Implement
creek restoration and water quality improvement projects by removing failing
concrete structures, recreating natural meanders, re-grading and stabilizing
banks using environmentally friendly techniques, and creating new habitat
areas with native creekside plants |
Master
project list, prioritization criteria, and initial project list approved by
City Council July 20, 2004.
Discussions underway with as-needed hydrology consultants for initial
projects, which include Shepherd Creek, Lion Creek at Coliseum Gardens,
Temescal Creek at Rockridge Greenbelt, and Cinderella Creek at Joaquin Miller
Park. |
| Watershed
Acquisition |
$4,500,000 |
$3,000,000 |
Acquire
creek and stream areas in order to preserve valuable creek habitats. Preservation of creek areas will improve
the quality of our water, create new open spaces and recreational
opportunities and will protect special wildlife habitats and unique natural
resources . |
Master project
list, prioritization criteria, and initial acquisition list approved by City
Council July 20, 2004. Discussions
with property owners for initial acquisitions underway. |
|
|
|
|
| Total |
|
$70,579,000
|
|
|
|
|
|
|
|
|
|
|
|